Contractor disputes in Ontario follow a familiar pattern. The work runs late, the price climbs, the quality falls short, or the job is abandoned half-finished, and the homeowner stops paying. From the contractor’s side, the story is often the mirror image: extra work was requested, invoices went unpaid, and the client moved the goalposts. Both sides usually have more legal tools, and more legal deadlines, than they realise. Knowing them early is what separates a dispute that settles from one that becomes expensive.
Start With the Contract
Where a homeowner hires a contractor for their own home, the contract is usually a consumer agreement governed by Ontario’s Consumer Protection Act, 2002. Several of its protections matter in renovation disputes.
Most renovation contracts are future performance agreements, because the work is done or paid for after the agreement is made. Where the consumer’s total payment obligation exceeds an amount set by regulation, section 22 requires those agreements to be in writing, delivered to the consumer and made in accordance with the prescribed requirements. If the consumer does not receive a copy of an agreement that meets those requirements, section 23 allows the consumer to cancel it within one year after entering into it.
Estimates are also regulated. Under section 10, if a consumer agreement includes an estimate, the supplier cannot charge more than 10 per cent above it, and if they do, the consumer may require that the work be provided at the estimated price. The parties can still agree to amend the price when the consumer asks for additional or different work, which is why change orders should be documented in writing. Section 9 deems the supplier to warrant that services are of a reasonably acceptable quality.
Ontario has passed a new consumer protection statute that will replace the 2002 Act once it is proclaimed in force. If that has happened by the time you read this, check which Act applied when your contract was signed. For work between businesses, the Consumer Protection Act does not apply, and the written contract carries even more weight.
Construction Liens: The Contractor’s Security, and Its Deadlines
Under section 14 of the Construction Act, a person who supplies services or materials to an improvement has a lien on the owner’s interest in the property for the price of those services or materials. For a contractor, the lien is a powerful form of security, because it can be registered against title to the home.
It is also strictly time-limited. A lien that attaches to the premises is preserved by registering a claim for lien on title under section 34. Under section 31, a contractor’s lien generally expires 60 days after the earlier of the publication of a certificate or declaration of substantial performance, or the date the contract is completed, abandoned or terminated. Even a preserved lien expires under section 36 unless it is perfected, by starting an action and registering a certificate of action, within 90 days after the last day on which it could have been preserved.
Missing these deadlines loses the lien. It does not necessarily end the underlying claim for payment, which can still be pursued as a breach of contract claim, but it loses the security that made the claim easier to collect.
The 10 Per Cent Holdback: What Homeowners Need to Know
Section 22 of the Construction Act requires each payer under a contract where a lien may arise to retain a holdback of 10 per cent of the price of the services or materials as they are supplied, until the liens that could be claimed against it have expired or been dealt with. The homeowner who pays the general contractor is a payer.
The reason this matters is section 23. An owner is personally liable for the holdbacks they were required to retain, to lien claimants with valid liens against the property. If the contractor fails to pay a subcontractor or supplier, and the homeowner has already paid the contractor in full without keeping the holdback, the homeowner can end up paying for part of the same work twice, up to the amount of the holdback they should have kept. Section 24 allows a payer to pay up to 90 per cent of the price of what has been supplied without that risk, unless they have received written notice of a lien.
Resolving Contractor Disputes in Ontario
For homeowners, document the problem as it develops: photographs, dates, messages, and independent quotes for completing or repairing the work. Put complaints in writing, and give the contractor any notice and opportunity to fix defects that the contract requires. Withholding payment can be justified, but withholding more than the defects are worth can turn you into the party in breach.
For contractors, keep the paperwork tight: written change orders, dated invoices, and a clear record of when work was last supplied, because that record drives the lien deadlines.
Many of these disputes are sized for Small Claims Court, which hears claims up to $50,000. Larger claims proceed in the Superior Court of Justice. If you have been served with a statement of claim over renovation or construction work, the time to respond is short; see what to do when you’re served with a statement of claim. Separate from the lien deadlines, the general two-year limitation period under the Limitations Act, 2002 applies to the contract claim.
If you are in a dispute with a contractor or a homeowner over renovation or construction work, George Habib, civil litigation lawyer at Habib Legal Counsel, will review the contract, the deadlines and your options. Visit HabibLC.com or call anytime at 647-648-2164 — George Habib and his firm are ready to help.